• What is Ivanpah?
  • Updates
  • News
  • Photos/Videos
  • Sign up for email updates

    I would like to receive email updates from BrightSource Energy about the Ivanpah project.


    Cancel
  • Recent Posts

    • Update from Ivanpah - May 2013 05.22.13
    • Ivanpah plant begins “steam blows” 04.05.13
    • Update from Ivanpah - February 2013 02.27.13
    • Ivanpah Project Reaches “First Flux” Milestone 02.27.13
    • Bechtel Construction Workers Give Back 02.25.13
    • Ivanpah: A Look Back at 2012 01.10.13
    • Ivanpah Team Installs 100,000th Heliostat 12.28.12
    • Update from Ivanpah – December 2012 12.17.12
    • Update from Ivanpah – October 2012 10.30.12
    • September Satellite Images Show Continued Solar Field Progress 10.10.12
    • Families of Ivanpah Enjoy a Sneak Peak at the Project 10.08.12
    • First Heliostats Successfully Aimed at the Unit 1 Boiler 09.18.12
    • Ivanpah Project and Local Community Colleges Partner for Educational Opportunities 09.17.12
    • Update from Ivanpah - August 2012 08.28.12
    • Recent Visitors to Ivanpah See Impressive Construction Progress 08.16.12
    • Updated Satellite Images Show Significant Solar Field Progress 08.15.12
    • Ivanpah Solar Project reaches halfway mark and peak of construction employment 08.07.12
    • Common Sense & Some Science Too…. 06.22.12
    • Update from Ivanpah - June 2012 06.19.12
    • Ivanpah Featured in NY Times Magazine 06.14.12
    • Steam Drum In Place at Unit 2 Tower 06.11.12
    • Satellite Imagery of Ivanpah Shows Low-Impact Design and Heliostat Progress 06.06.12
    • Secretary Salazar Visits Ivanpah Project 05.17.12
    • Ivanpah project begins springtime tortoise translocations 04.26.12
    • Update from Ivanpah - April 2012 04.18.12
    • Desert Tortoise Care at the Ivanpah Solar Project 03.06.12
    • Update from Ivanpah - February 2012 02.23.12
    • Ivanpah Wins CSP Project of the Year Award 02.21.12
    • The Ivanpah Solar Project: Getting the Facts Straight 02.07.12
    • Construction Highlights: October and November 12.16.11
    • Aerials from Ivanpah SEGS - November 2011 12.06.11
    • First Heliostat Placed on a Pylon 11.04.11
    • Secretary Salazar Visits Ivanpah 10.26.11
    • Construction Highlights: August and September 2011 10.26.11
    • Ivanpah's First Translocated Tortoise 10.26.11
    • Happy Birthday Ivanpah! 10.26.11
    • Ivanpah’s First Heliostat 10.24.11
    • First tortoise translocation at Ivanpah 10.10.11
    • Ivanpah Unit 1 progress highlights 09.20.11
    • Meet Ross and Kenneth, Teamster Apprentices at the Ivanpah Solar Electric Generating System (ISEGS) 08.17.11
    • Ivanpah progress highlights: Summer is in full swing in the Mojave Desert 08.17.11
    • Aerial views of progress at the Ivanpah construction site 07.13.11
    • Ivanpah Steel Supplier’s New Manufacturing Plant in Arizona is Progressing on Schedule 07.01.11
    • BLM Approves Next Phase of Construction at Ivanpah Solar Electric Generating System 06.10.11
    • BrightSource Energy Establishes “Head-Start” Program for Desert Tortoise 06.10.11
    • Eldorado-Ivanpah Transmission Project Approved 06.08.11
    • Ivanpah progress highlights 06.07.11
    • Meet Max Havelka, Desert Tortoise Biologist 06.06.11
    • First Pylons Installed at Ivanpah Unit 1 05.11.11
    • BrightSource Closes Financing for the Ivanpah Project 04.12.11
    • Photo from Ivanpah construction – April 2011 04.04.11
    • Ivanpah Steel Supplier Breaks Ground on New Manufacturing Plant in Arizona 03.03.11
    • Ivanpah Supplier Cone Drive Gearing Solutions featured in the Traverse City Record-Eagle 03.03.11
    • Ivanpah Creating Domestic Jobs in Rust Belt 01.25.11
    • BrightSource’s Ivanpah Plant Featured in CSP Today for Producing “Sustainable and Responsible” Clean Energy 11.29.10
    • BrightSource formally breaks ground at Ivanpah 10.27.10
    • NRG partners with BrightSource and joins the Ivanpah family! 10.27.10
    • BrightSource secures all three steam turbine generators needed for Ivanpah 10.14.10
    • Ivanpah receives its final permits! 10.07.10
    • President Obama Gives Ivanpah Kudos 10.02.10
    • Green light from the California Energy Commission 09.22.10
    • What’s a boiler? BrightSource is purchasing three from Riley Power Inc. 09.09.10
    • Approval from the California Public Utilities Commission 08.12.10
  • Follow Us

What's New

Updates News Photos/Videos
02.23.12

Update from Ivanpah – February 2012


Time-Lapse Video of Ivanpah SEGS Unit #1 Construction

In just over one year’s time, Ivanpah’s Unit #1 tower has climbed an impressive 400 feet! An aerial camera positioned high above the solar project has captured the tower’s construction. Click the video to watch a short time-lapse video of the tower’s rapid ascent.

Construction Update 

The Ivanpah SEGS site entered the New Year with a bang. Construction of the solar plant is advancing on schedule, with over 1200 workers busy erecting the steel towers, preparing and installing heliostats, building solar boiler sections and much more. The team achieved great progress over the holidays and in the first month of the year. See below for construction highlights from December and January.

View from the top of the Unit #1 tower looking over the Ivanpah SEGS

Common Area

The heliostat assembly building with mirrors ready for transport to the solar fie

In the Common Area, the Pad Bonding Buildings and the Heliostat Assembly Building are nearing full production capacity. The heliostat assembly facility is approaching its goal of assembling 500 heliostats each day.

Construction on the permanent administration buildings continues to move forward, with roofing placed in January. Trenching and pipe-laying is underway for the natural gas pipeline. The project pipeline will interconnect with the existing Kern River Gas Transmission system to allow delivery of natural gas to Unit #1, Unit #2 and Unit #3.

Unit 1

Unit #1 tower and power block

In the Unit #1 solar field, pylon installation continues, with more than 90 percent of the total 53,500 pylons that will be installed in the Unit #1 solar field. The team is installing heliostats onto the pylons in the solar field, with more than 8,000 heliostats installed to date. Tractors pull wagons with specially designed racks that hold the completed heliostats into the solar field. Cranes lift the heliostats off of the racks and place them on the pylon where they are manually secured.

The Unit #1 tower now measures more than 400 feet. All nine steel sections of the tower are complete and the team has lifted four of the five solar receiver steam generator (SRSG, or boiler) sections into place. Work continues on installing the piping and conduit, while the remaining boiler section is built on the ground in preparation for a lift into place by crane in the coming weeks. As the boiler work nears completion, protective panels are installed onto the boiler. We are rapidly nearing a final height of 450-feet for the Unit #1 tower.

Heliostats are transported to Unit #1 solar field

In the Unit #1 power block area, work continues on the steam turbine, air-cooled condenser (ACC) and plant services building. The steam turbine generator is now aligned on its foundation, and the plant service building is enclosed. The team will begin installing electrical equipment in the coming weeks.

The first A-frame for the ACC and is now set into place. The ACC allows Ivanpah to be “dry-cooled” versus wet-cooled, reducing water usage by more than 90% over using conventional wet cooling systems.

Unit 2

Unit #2 tower and power block

Eight steel sections are now in place at the Unit #2 tower that stands at more than 300 feet. The remaining sections of the tower are being built on the ground in the power block area and will be lifted into place by crane. The team is assembling the boiler sections to be lifted into place once the nine steel sections are complete. In the power block area, general earth work is ongoing, including the completion of concrete foundations for the plant service building and steam turbine generator.

In the solar field, the team has completed the “ring roads,” or dirt paths placed within the solar field to allow workers to access the heliostats and wash the heliostat mirrors. More than 14% of the total pylons needed have been inserted in the Unit #2 solar field, and a few hundred heliostats are installed as well.

Unit 3

Unit #3 tower and power block

At Unit #3, the team placed the concrete foundation for the tower in December, and set the first tower steel in January. Tower erection is now through tier two. General earthwork is ongoing as the team prepares for concrete placements for the plant services building, ACC and steam turbine generator.

The team assembled the tower crane in preparation for lifting steel sections into place. An interesting fact – there are only 22 tower cranes of this kind in the world, and the Ivanpah SEGS is currently home to three!

Ivanpah Wins “CSP Project of the Year” Award from Solar Power Generation

BrightSource's Mike Bobinecz (left) accepts the "CSP Project of the Year" award from Solar Power Generation USA.

On January 28, 2012, Solar Power Generation USA recognized the Ivanpah SEGS with the “CSP Project of the Year” honor, a prestigious award given by the leading industry conference organizing group. The award was accepted by BrightSource’s Mike Bobinecz, Project Director and Vice President, BrightSource Construction Management, BrightSource Energy. Solar Power Generation selected Ivanpah for the award for the significant impact the project will have in advancing solar thermal electricity production in the US. Additionally, Solar Power Generation commended Ivanpah as a great example of how a well-structured, large-scale project can still attract the necessary investment to succeed.

Home What is Ivanpah? What's New
www.brightsourceenergy.com
©2013 BrightSource Energy, Inc. All rights reserved.