• What is Ivanpah?
  • Updates
  • News
  • Photos/Videos
  • Sign up for email updates

    I would like to receive email updates from BrightSource Energy about the Ivanpah project.


    Cancel
  • Recent Posts

    • Update from Ivanpah - May 2013 05.22.13
    • Ivanpah plant begins “steam blows” 04.05.13
    • Update from Ivanpah - February 2013 02.27.13
    • Ivanpah Project Reaches “First Flux” Milestone 02.27.13
    • Bechtel Construction Workers Give Back 02.25.13
    • Ivanpah: A Look Back at 2012 01.10.13
    • Ivanpah Team Installs 100,000th Heliostat 12.28.12
    • Update from Ivanpah – December 2012 12.17.12
    • Update from Ivanpah – October 2012 10.30.12
    • September Satellite Images Show Continued Solar Field Progress 10.10.12
    • Families of Ivanpah Enjoy a Sneak Peak at the Project 10.08.12
    • First Heliostats Successfully Aimed at the Unit 1 Boiler 09.18.12
    • Ivanpah Project and Local Community Colleges Partner for Educational Opportunities 09.17.12
    • Update from Ivanpah - August 2012 08.28.12
    • Recent Visitors to Ivanpah See Impressive Construction Progress 08.16.12
    • Updated Satellite Images Show Significant Solar Field Progress 08.15.12
    • Ivanpah Solar Project reaches halfway mark and peak of construction employment 08.07.12
    • Common Sense & Some Science Too…. 06.22.12
    • Update from Ivanpah - June 2012 06.19.12
    • Ivanpah Featured in NY Times Magazine 06.14.12
    • Steam Drum In Place at Unit 2 Tower 06.11.12
    • Satellite Imagery of Ivanpah Shows Low-Impact Design and Heliostat Progress 06.06.12
    • Secretary Salazar Visits Ivanpah Project 05.17.12
    • Ivanpah project begins springtime tortoise translocations 04.26.12
    • Update from Ivanpah - April 2012 04.18.12
    • Desert Tortoise Care at the Ivanpah Solar Project 03.06.12
    • Update from Ivanpah - February 2012 02.23.12
    • Ivanpah Wins CSP Project of the Year Award 02.21.12
    • The Ivanpah Solar Project: Getting the Facts Straight 02.07.12
    • Construction Highlights: October and November 12.16.11
    • Aerials from Ivanpah SEGS - November 2011 12.06.11
    • First Heliostat Placed on a Pylon 11.04.11
    • Secretary Salazar Visits Ivanpah 10.26.11
    • Construction Highlights: August and September 2011 10.26.11
    • Ivanpah's First Translocated Tortoise 10.26.11
    • Happy Birthday Ivanpah! 10.26.11
    • Ivanpah’s First Heliostat 10.24.11
    • First tortoise translocation at Ivanpah 10.10.11
    • Ivanpah Unit 1 progress highlights 09.20.11
    • Meet Ross and Kenneth, Teamster Apprentices at the Ivanpah Solar Electric Generating System (ISEGS) 08.17.11
    • Ivanpah progress highlights: Summer is in full swing in the Mojave Desert 08.17.11
    • Aerial views of progress at the Ivanpah construction site 07.13.11
    • Ivanpah Steel Supplier’s New Manufacturing Plant in Arizona is Progressing on Schedule 07.01.11
    • BLM Approves Next Phase of Construction at Ivanpah Solar Electric Generating System 06.10.11
    • BrightSource Energy Establishes “Head-Start” Program for Desert Tortoise 06.10.11
    • Eldorado-Ivanpah Transmission Project Approved 06.08.11
    • Ivanpah progress highlights 06.07.11
    • Meet Max Havelka, Desert Tortoise Biologist 06.06.11
    • First Pylons Installed at Ivanpah Unit 1 05.11.11
    • BrightSource Closes Financing for the Ivanpah Project 04.12.11
    • Photo from Ivanpah construction – April 2011 04.04.11
    • Ivanpah Steel Supplier Breaks Ground on New Manufacturing Plant in Arizona 03.03.11
    • Ivanpah Supplier Cone Drive Gearing Solutions featured in the Traverse City Record-Eagle 03.03.11
    • Ivanpah Creating Domestic Jobs in Rust Belt 01.25.11
    • BrightSource’s Ivanpah Plant Featured in CSP Today for Producing “Sustainable and Responsible” Clean Energy 11.29.10
    • BrightSource formally breaks ground at Ivanpah 10.27.10
    • NRG partners with BrightSource and joins the Ivanpah family! 10.27.10
    • BrightSource secures all three steam turbine generators needed for Ivanpah 10.14.10
    • Ivanpah receives its final permits! 10.07.10
    • President Obama Gives Ivanpah Kudos 10.02.10
    • Green light from the California Energy Commission 09.22.10
    • What’s a boiler? BrightSource is purchasing three from Riley Power Inc. 09.09.10
    • Approval from the California Public Utilities Commission 08.12.10
  • Follow Us

What's New

Updates News Photos/Videos
12.16.11

Construction Highlights: October and November

With over a year under our belt, construction of the Ivanpah SEGS plant continues to progress on schedule. The nearly 1,000 workers on site have accomplished a great deal over the past two months – the Unit 1 structural tower is nearly complete, the heliostats are being assembled and placed onto pylons in the field, Unit 2 continues structural tower erection and has commenced pylon insertion and the Unit 3 structural tower is nearly ready for the foundation pour. Below are a few highlights from October and November.

The ISEGS Common Area, includes heliostat assembly buildings, construction laydown area, administrative areas, etc. (November 2011)

Common Area

In the Common Area, commissioning of equipment in the Heliostat Assembly Building and the Pad Bonding Buildings are in the final stages. In October and November, heliostats were produced and production significantly ramped-up in December. In 2012, we anticipate hundreds of heliostats will be assembled and installed each day. Additionally, we began construction of the permanent administration buildings.

Ivanpah Unit 1 power block and framing for the air-cooled condenser. (November 2011)

Unit 1

At the Unit 1 solar field, pylon installation continues, with over 40,000 pylons currently in place – over 75% of the total 50,000+ pylons that will be installed in the Unit 1 solar field. Each pylon will eventually carry one heliostat consisting of two large mirrors. The pylons are inserted directly into the ground, without any grading or concrete, allowing vegetation to coexist in the solar field. Pylons are arranged in concentric circles around the tower so that the heliostats can track the sun.

The Unit 1 tower reached roughly 300 feet by the end of November. Currently, eight out of nine tier steel sections of the tower are in place. The final steel section and the solar receiver steam generator (SRSG, or boiler) are being built on the ground and will be lifted by crane into place in coming months. Once complete, the structure, including the boiler will stand at 450-feet.

In the Unit 1 power block area, work on the steam turbine and air-cooled condenser (ACC) is progressing rapidly. The steam turbine and generator have been set on the foundation and assembly has commenced. The ACC allows Ivanpah to be “dry-cooled” versus wet-cooled, reducing water usage by more than 90% over competing solar thermal technologies using conventional wet cooling systems. The supporting structure of the ACC is under construction.

Ivanpah Unit 2 power block. (November 2011)

Unit 2

Three steel sections are in place at the Unit 2 tower which stands at 120 feet. Once the 4th section is stick built, the remaining sections of the tower that are being built on the ground in the power block area, will be lifted into place by crane. Concrete placement for the ACC foundation is also underway in the power block. Pylon installation has commenced in the Unit 2 solar field.

Ivanpah Unit 3 power block. (November 2011)

Unit 3

At Unit 3, first concrete was achieved this month with the placement of foundation at the plant services building base mat. The steam turbine and tower foundation pours are expected to be complete by year-end. In the Unit 3 solar field, fencing, clearing and roadwork continue.

Home What is Ivanpah? What's New
www.brightsourceenergy.com
©2013 BrightSource Energy, Inc. All rights reserved.