• What is Ivanpah?
  • Updates
  • News
  • Photos/Videos
  • Sign up for email updates

    I would like to receive email updates from BrightSource Energy about the Ivanpah project.


    Cancel
  • Recent Posts

    • Update from Ivanpah - May 2013 05.22.13
    • Ivanpah plant begins “steam blows” 04.05.13
    • Update from Ivanpah - February 2013 02.27.13
    • Ivanpah Project Reaches “First Flux” Milestone 02.27.13
    • Bechtel Construction Workers Give Back 02.25.13
    • Ivanpah: A Look Back at 2012 01.10.13
    • Ivanpah Team Installs 100,000th Heliostat 12.28.12
    • Update from Ivanpah – December 2012 12.17.12
    • Update from Ivanpah – October 2012 10.30.12
    • September Satellite Images Show Continued Solar Field Progress 10.10.12
    • Families of Ivanpah Enjoy a Sneak Peak at the Project 10.08.12
    • First Heliostats Successfully Aimed at the Unit 1 Boiler 09.18.12
    • Ivanpah Project and Local Community Colleges Partner for Educational Opportunities 09.17.12
    • Update from Ivanpah - August 2012 08.28.12
    • Recent Visitors to Ivanpah See Impressive Construction Progress 08.16.12
    • Updated Satellite Images Show Significant Solar Field Progress 08.15.12
    • Ivanpah Solar Project reaches halfway mark and peak of construction employment 08.07.12
    • Common Sense & Some Science Too…. 06.22.12
    • Update from Ivanpah - June 2012 06.19.12
    • Ivanpah Featured in NY Times Magazine 06.14.12
    • Steam Drum In Place at Unit 2 Tower 06.11.12
    • Satellite Imagery of Ivanpah Shows Low-Impact Design and Heliostat Progress 06.06.12
    • Secretary Salazar Visits Ivanpah Project 05.17.12
    • Ivanpah project begins springtime tortoise translocations 04.26.12
    • Update from Ivanpah - April 2012 04.18.12
    • Desert Tortoise Care at the Ivanpah Solar Project 03.06.12
    • Update from Ivanpah - February 2012 02.23.12
    • Ivanpah Wins CSP Project of the Year Award 02.21.12
    • The Ivanpah Solar Project: Getting the Facts Straight 02.07.12
    • Construction Highlights: October and November 12.16.11
    • Aerials from Ivanpah SEGS - November 2011 12.06.11
    • First Heliostat Placed on a Pylon 11.04.11
    • Secretary Salazar Visits Ivanpah 10.26.11
    • Construction Highlights: August and September 2011 10.26.11
    • Ivanpah's First Translocated Tortoise 10.26.11
    • Happy Birthday Ivanpah! 10.26.11
    • Ivanpah’s First Heliostat 10.24.11
    • First tortoise translocation at Ivanpah 10.10.11
    • Ivanpah Unit 1 progress highlights 09.20.11
    • Meet Ross and Kenneth, Teamster Apprentices at the Ivanpah Solar Electric Generating System (ISEGS) 08.17.11
    • Ivanpah progress highlights: Summer is in full swing in the Mojave Desert 08.17.11
    • Aerial views of progress at the Ivanpah construction site 07.13.11
    • Ivanpah Steel Supplier’s New Manufacturing Plant in Arizona is Progressing on Schedule 07.01.11
    • BLM Approves Next Phase of Construction at Ivanpah Solar Electric Generating System 06.10.11
    • BrightSource Energy Establishes “Head-Start” Program for Desert Tortoise 06.10.11
    • Eldorado-Ivanpah Transmission Project Approved 06.08.11
    • Ivanpah progress highlights 06.07.11
    • Meet Max Havelka, Desert Tortoise Biologist 06.06.11
    • First Pylons Installed at Ivanpah Unit 1 05.11.11
    • BrightSource Closes Financing for the Ivanpah Project 04.12.11
    • Photo from Ivanpah construction – April 2011 04.04.11
    • Ivanpah Steel Supplier Breaks Ground on New Manufacturing Plant in Arizona 03.03.11
    • Ivanpah Supplier Cone Drive Gearing Solutions featured in the Traverse City Record-Eagle 03.03.11
    • Ivanpah Creating Domestic Jobs in Rust Belt 01.25.11
    • BrightSource’s Ivanpah Plant Featured in CSP Today for Producing “Sustainable and Responsible” Clean Energy 11.29.10
    • BrightSource formally breaks ground at Ivanpah 10.27.10
    • NRG partners with BrightSource and joins the Ivanpah family! 10.27.10
    • BrightSource secures all three steam turbine generators needed for Ivanpah 10.14.10
    • Ivanpah receives its final permits! 10.07.10
    • President Obama Gives Ivanpah Kudos 10.02.10
    • Green light from the California Energy Commission 09.22.10
    • What’s a boiler? BrightSource is purchasing three from Riley Power Inc. 09.09.10
    • Approval from the California Public Utilities Commission 08.12.10
  • Follow Us

What's New

Updates News Photos/Videos
10.26.11

Construction Highlights: August and September 2011

Key Statistics

Common Area
In the Common Area, work in the Heliostat Assembly Building and the Pad Bonding Buildings continue to progress. We continue to ramp-up for production and assembly of the heliostats before they are placed on the pylons in the solar field. The commissioning of machinery is almost complete and we hope to install thousands of heliostats this fall.

Unit 1

Tiers 1-4 in position at the Unit 1 Power Tower

At the Unit 1 solar field, pylon installation continues, with over 20,000 pylons currently in place – almost 40% of the total 50,000+ pylons that will be installed in the Unit 1 solar field. Each pylon will eventually carry two flat mirrors (making one heliostat). The pylons are inserted directly into the ground, without any grading or concrete, letting vegetation coexist with the heliostat in the solar field. Pylons are arranged in concentric circles around the power tower so their mirrors can track the sun.

While the number of pylons in the solar field increases each day, the height of the Unit 1 tower continues to grow. Currently, four out of nine total steel sections of the tower have been put in place. Once complete, the structure, including the boiler will stand at 450-foot.

With only a few more tiers to go on the Unit 1 tower and total pylon installation nearing the halfway mark, this unit of the ISEGS is steadily building out toward completion.

Unit 2

The first steel is placed for the Unit 2 Power Tower

Unit 2 has reached its own milestone with the erection of the first structural steel section of the solar power boiler. A large tower crane is being assembled to place the remaining sections of the tower, which are being built in the power block area and then lifted into place. In the Unit 2 solar field, trained desert biologists completed their efforts to move the tortoise remaining on the project site to the temporary nursery pens.

Unit 3

Foundation work begins for the Unit 3 Power Block

At Unit 3, foundation preparation is underway for the power block area. Once complete, there will be a concrete placement for the tower base followed by the erection of the structural steel. Similar to the cement placements at Unit 1 and Unit 2, the foundation will require approximately 500 truckloads of concrete.

Home What is Ivanpah? What's New
www.brightsourceenergy.com
©2013 BrightSource Energy, Inc. All rights reserved.